Caltrans Logo

Install Mobile Data Terminal

Description: Purchase up to 460 Mobile Data Terminals on all vanpool vehicles

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kings
City Hanford
Zip Code 93232
 
Senate District
16
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  15    15  
Increased Ridership  5    5  
Reduced Emissions  25    25  
Reduced Operating/Maintenance Cost  15    15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RONALD HUGHES (559) 852-3211   RON.HUGHES@CO.KINGS.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$30 $-30 $0
PTMISEA-99313
$600 $-127 $473
Non-bond Funding
 
Total**** $630 $-157 $473

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$630 $-157 $473 $473 $473 $0
 
Total* $630 $-157 $473 $473 $473 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2009 

11/30/2009 
02/24/2011 

02/24/2011 
11/01/2009 

11/30/2009 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2009 

12/31/2009 
02/24/2011 

02/24/2011 
12/01/2009 

12/31/2009 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2010 

05/30/2010 
02/24/2011 

02/24/2011 
01/01/2010 

12/30/2010 
 

 


Begin Closeout Phase

End Closeout Phase
06/01/2010 

06/30/2010 
02/24/2011 

02/24/2011 
01/01/2011 

02/11/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 15 15
Increased Ridership 5 5
Reduced Emissions 25 25
Reduced Operating/Maintenance Cost 15 15

Bond Funding Cost
Adopted:
$629,576
Current Approved:
$472,769
Actual Expenditures:
$472,769

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31