Description: Project will result in new wayfinding signage, real-time transit information displays and printing transit information displays (TIDs) at 21 regional transit hubs and 3 airports
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Oakland, Ca |
Zip Code | 94607 |
Senate District |
01, 06, 07, 08, 10, 11, 12, 13, 14, 15, 16, 18, 19, 20, 21, 22, 23, 24, 27, 28 |
Assembly District | 02, 03, 05, 07, 08, 09, 10, 11, 13, 15 |
Congressional District | 26 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 2 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
PIERCE GOULD | (510) 817-5863 | PGOULD@MTC.CA.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $41 | $41 | ||||
PTMISEA-99313 |
$9,858 | $-280 | $9,578 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $3,168 | $3,168 | ||||
Local** |
$0 | $148 | $148 | ||||
Total**** | $9,858 | $3,077 | $12,935 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$1,578 | $-1,578 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,380 | $-1,380 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,900 | $6,035 | $12,935 | $9,767 | $9,767 | $3,168 | |
Total* | $9,858 | $3,077 | $12,935 | $9,767 | $9,767 | $3,168 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/25/2008 03/31/2011 |
03/21/2017 |
01/25/2008 04/30/2017 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
10/31/2008 03/31/2009 |
03/15/2010 03/21/2017 |
11/01/2008 06/30/2017 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2009 09/30/2009 |
03/15/2010 03/21/2017 |
03/25/2009 04/30/2018 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
10/31/2009 03/31/2010 |
03/21/2017 03/21/2017 |
05/01/2018 06/30/2018 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
$9,858,000 |
Current Approved: |
$9,578,000 |
Actual Expenditures: |
$9,578,000 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31