Caltrans Logo

Transit Connectivity

Description: Project will result in new wayfinding signage, real-time transit information displays and printing transit information displays (TIDs) at 21 regional transit hubs and 3 airports

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland, Ca
Zip Code 94607
 
Senate District
01, 06, 07, 08, 10, 11, 12, 13, 14, 15, 16, 18, 19, 20, 21, 22, 23, 24, 27, 28
Assembly District 02, 03, 05, 07, 08, 09, 10, 11, 13, 15
Congressional District 26
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PIERCE GOULD (510) 817-5863   PGOULD@MTC.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $41 $41
PTMISEA-99313
$9,858 $-280 $9,578
Non-bond Funding
State/Federal*
$0 $3,168 $3,168
Local**
$0 $148 $148
 
Total**** $9,858 $3,077 $12,935

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$1,578 $-1,578 $0 $0 $0 $0
Design(PS&E)
$1,380 $-1,380 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,900 $6,035 $12,935 $9,767 $9,767 $3,168
 
Total* $9,858 $3,077 $12,935 $9,767 $9,767 $3,168

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/25/2008 

03/31/2011 
 

03/21/2017 
01/25/2008 

04/30/2017 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/31/2008 

03/31/2009 
03/15/2010 

03/21/2017 
11/01/2008 

06/30/2017 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/30/2009 

09/30/2009 
03/15/2010 

03/21/2017 
03/25/2009 

04/30/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
10/31/2009 

03/31/2010 
03/21/2017 

03/21/2017 
05/01/2018 

06/30/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2

Bond Funding Cost
Adopted:
$9,858,000
Current Approved:
$9,578,000
Actual Expenditures:
$9,578,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31