E Street Transit Corridor Project (sbx)

Description: Implement new BRT system

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92411
 
Senate District
32
Assembly District 62
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      3  
Increased Ridership  35    65  
Useful Life (years)  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Omnitrans Rohan Kuruppu (909) 379-7251   rohan.kruruppu@omnitrans.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $57 $57
PTMISEA-99313
$3,271 $3,429 $6,700
PTMISEA-99314
$0 $724 $724
Non-bond Funding
State/Federal*
$93,687 $4,100 $97,787
Local**
$14,563 $-10,321 $4,242
 
Total**** $111,521 $-2,010 $109,511

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$9,424 $1,729 $11,153 $0 $0 $11,153
Design(PS&E)
$0 $0 $0 $7,131 $7,131 $-7,131
Right of Way
$0 $7,425 $7,425 $293 $293 $7,131
Construction
$102,097 $-11,164 $90,933 $57 $57 $90,876
 
Total* $111,521 $-2,010 $109,511 $7,482 $7,482 $102,029

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2007 

01/01/2009 
 

 
06/01/2007 

01/01/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2009 

07/01/2010 
 

03/14/2011 
04/01/2009 

09/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
03/29/2013 

09/06/2013 
05/01/2010 

04/01/2013 
100   

 


Begin Construction Phase

End Construction Phase
02/01/2010 

07/01/2012 
09/06/2012 

02/10/2017 
10/01/2011 

04/30/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
 

12/01/2011 
03/03/2020 

03/03/2020 
01/01/2016 

02/27/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 3
Increased Ridership 35 65
Useful Life (years) 15

Bond Funding Cost
Adopted:
$3,270,981
Current Approved:
$7,424,514
Actual Expenditures:
$7,424,514

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31