Caltrans Logo

ITS Hardware/software for buses

Description: Installation of ITS equipment on buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Hesperia
Zip Code 92345
 
Senate District
17
Assembly District 59
Congressional District 41
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      20  
Increase System Reliability (percent)  20      
Useful Life (years)  2      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Victor Valley Transit Authority Kevin Kane (760) 948-4330   kkane@vvta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $4 $4
PTMISEA-99313
$150 $0 $150
Non-bond Funding
State/Federal*
$1,094 $-128 $966
Local**
$273 $6 $279
 
Total**** $1,517 $-118 $1,399

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,517 $-118 $1,399 $154 $154 $1,245
 
Total* $1,517 $-118 $1,399 $154 $154 $1,245

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2008 

11/01/2008 
06/21/2010 

06/21/2010 
09/21/2009 

01/31/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2008 

12/01/2008 
06/21/2010 

06/21/2010 
12/01/2010 

01/31/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20
Increase System Reliability (percent) 20
Useful Life (years) 2

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$150,000
Actual Expenditures:
$150,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31