Intermodal Transit Center

Description: Construct new transit center

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Barbara
City Santa Maria
Zip Code 93458
 
Senate District
15
Assembly District 33
Congressional District 23
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    20  
Increased Ridership  15      
Useful Life (years)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Santa Maria Austin O'Dell (805) 925-0951 X480   aodell@ci.santa-maria.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$1,456 $0 $1,456
PTMISEA-99314
$107 $0 $107
Non-bond Funding
State/Federal*
$3,230 $530 $3,761
Local**
$4,160 $-20 $4,140
 
Total**** $8,953 $510 $9,463

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$495 $245 $740 $0 $0 $740
Right of Way
$3,765 $-265 $3,500 $0 $0 $3,500
Construction
$4,693 $530 $5,223 $1,632 $1,632 $3,592
 
Total* $8,953 $510 $9,463 $1,632 $1,632 $7,831

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
07/01/2008 

09/30/2008 
10/06/2011 

10/06/2011 
01/01/2011 

04/01/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2008 

11/30/2008 
10/06/2011 

10/06/2011 
04/01/2011 

09/01/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 20
Increased Ridership 15
Useful Life (years) 30

Bond Funding Cost
Adopted:
$1,562,671
Current Approved:
$1,562,671
Actual Expenditures:
$1,562,671

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31