Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
MetroBase Operations Facility |
Description: Operations Facility In Santa Cruz
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Santa Cruz |
City | Santa Cruz |
Zip Code | 95060 |
Senate District |
11, 15 |
Assembly District | 27, 28 |
Congressional District | 14, 17 |
Caltrans District |
05 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 3 | |
Reduce Emissions (percent) | 93 | |
Reduced Emissions | 3 | |
Reduced Operating/Maintenance Cost | 5 | |
Useful Life (years) | 20 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Santa Cruz Metropolitan Transit District | Thomas Hiltner | (831) 426-6080 | thiltner@scmtd.com |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $420 | $420 | ||||
PTMISEA-99313 |
$9,827 | $1,675 | $11,502 | ||||
PTMISEA-99314 |
$10,560 | $69 | $10,629 | ||||
Non-bond Funding | |||||||
State/Federal* |
$24,896 | $9,592 | $34,488 | ||||
Local** |
$13,109 | $6,783 | $19,892 | ||||
Total**** | $58,392 | $18,539 | $76,931 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$318 | $1,272 | $1,590 | $0 | $0 | $1,590 | |
Design(PS&E) |
$3,002 | $1,846 | $4,848 | $4,143 | $4,143 | $705 | |
Right of Way |
$1,750 | $7,748 | $9,498 | $5,578 | $5,578 | $3,920 | |
Construction |
$53,322 | $7,672 | $60,994 | $67,765 | $67,765 | $-6,771 | |
Total* | $58,392 | $18,539 | $76,931 | $77,487 | $77,487 | $-556 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
08/24/2009 08/24/2009 |
04/01/2002 02/01/2003 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
10/24/2008 10/24/2008 |
12/01/2003 02/28/2009 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
08/24/2009 08/24/2009 |
02/01/2003 04/01/2005 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
12/01/2005 06/30/2011 |
09/30/2016 09/30/2016 |
12/01/2009 12/01/2019 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/30/2011 12/30/2011 |
10/16/2018 10/16/2018 |
03/01/2018 12/01/2018 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 3 | |
Reduce Emissions (percent) | 93 | |
Reduced Emissions | 3 | |
Reduced Operating/Maintenance Cost | 5 | |
Useful Life (years) | 20 |
Bond Funding Cost | |
---|---|
Adopted: |
$20,386,899 |
Current Approved: |
$22,130,731 |
Actual Expenditures: |
$22,130,731 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31