IVC Bus Transfer Terminal

Description: Construction of Imperial Valley College Bus Transfer Terminal (Phase I)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City El Centro
Zip Code 92243
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHI WILLIAMS (760) 482-4290   KATHIWILLIAMS@CO.IMPERIAL.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$1,333 $-169 $1,164
Non-bond Funding
 
Total**** $1,333 $-169 $1,164

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$129 $-104 $25 $25 $25 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,204 $-65 $1,139 $1,139 $1,139 $0
 
Total* $1,333 $-169 $1,164 $1,164 $1,164 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2008 

04/01/2008 
 

 
03/01/2008 

04/01/2008 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2008 

09/01/2008 
 

 
06/01/2008 

09/01/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2008 

05/01/2009 
 

08/24/2010 
06/01/2009 

06/30/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2009 

06/01/2009 
08/24/2010 

08/24/2010 
07/01/2010 

10/01/2010 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Increased Ridership 5

Bond Funding Cost
Adopted:
$1,333,071
Current Approved:
$1,163,867
Actual Expenditures:
$1,163,867

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31