GGBHTD Ferry Vessel Replacement |
Description: Project is to purchase and refurbish two used ferry vessels
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Marin |
City | San Francisco |
Zip Code | 94129 |
Senate District |
03, 08 |
Assembly District | 06, 12, 13 |
Congressional District | |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Ridership (percent) | 6 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
Golden Gate Bridge,Highway & Transportation District | Gayle Prior | (415) 923-2373 | gprior@goldengate.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99314 |
$2,116 | $0 | $2,116 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,600 | $9,611 | $19,211 | ||||
Local** |
$284 | $2,524 | $2,807 | ||||
Total**** | $12,000 | $12,135 | $24,135 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$1,000 | $0 | $1,000 | $0 | $0 | $1,000 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$11,000 | $12,135 | $23,135 | $23,278 | $23,278 | $-143 | |
Total* | $12,000 | $12,135 | $24,135 | $23,278 | $23,278 | $857 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2007 09/01/2008 |
|
05/01/2007 09/01/2008 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2009 10/01/2011 |
08/15/2013 08/15/2013 |
04/22/2010 04/13/2012 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/01/2011 12/01/2011 |
08/15/2013 08/15/2013 |
04/13/2012 04/13/2013 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase in Ridership (percent) | 6 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,116,322 |
Current Approved: |
$2,116,322 |
Actual Expenditures: |
$2,116,322 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31