LAVTA Bus Stop Improvements

Description: Project will enhance key bus stops with shelters, lighting, signage, solar panels, and access improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Dublin, Livermore, Pleasanton
Zip Code 94551
 
Senate District
09, 10
Assembly District 15, 18
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      12  
Increase in Ridership (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Livermore-Amadore Valley Transit Authority Tamara Edwards 925-455-7566   tedwards@lavta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$100 $0 $100
Non-bond Funding
Local**
$0 $21 $21
 
Total**** $100 $23 $123

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$100 $23 $123 $123 $123 $0
 
Total* $100 $23 $123 $123 $123 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2008 

08/01/2008 
 

03/17/2010 
06/01/2008 

07/01/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2008 

10/01/2008 
01/21/2009 

01/21/2009 
06/01/2009 

07/01/2009 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 12
Increase in Ridership (percent)

Bond Funding Cost
Adopted:
$100,000
Current Approved:
$101,861
Actual Expenditures:
$101,861

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31