Caltrans Logo

Santa Clara VTA Blossom Hill/Monterey Hwy. Ped O/C

Description: Project will construct a safe grade separated crossing over the Union Pacific railroad tracks south of Blossom Hill Road

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Santa Clara
City San Jose
Zip Code 95134
 
Senate District
11
Assembly District 23
Congressional District
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      100  
Safety Improvement (percent)        
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Santa Clara Valley Transportation Authority Liz French (408) 321-5737   liz.french@vta.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $501 $501
PTMISEA-99314
$6,790 $0 $6,790
Non-bond Funding
State/Federal*
$2,480 $-10 $2,470
Local**
$1,230 $205 $1,435
 
Total**** $10,500 $696 $11,196

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$110 $-110 $0 $0 $0 $0
Design(PS&E)
$1,120 $76 $1,196 $3,115 $3,115 $-1,919
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$9,270 $730 $10,000 $8,080 $8,080 $1,919
 
Total* $10,500 $696 $11,196 $11,196 $11,196 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2008 

12/01/2008 
 

 
02/01/2008 

02/28/2009 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2008 

04/01/2009 
 

10/26/2010 
12/01/2008 

04/01/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
10/26/2010 

10/26/2010 
07/01/2009 

05/31/2010 
100   

 


Begin Construction Phase

End Construction Phase
09/01/2009 

09/01/2010 
03/29/2011 

02/26/2013 
01/01/2011 

01/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2010 

12/01/2010 
02/24/2016 

02/24/2016 
12/31/2016 

07/01/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100
Safety Improvement (percent)

Bond Funding Cost
Adopted:
$6,790,000
Current Approved:
$6,790,000
Actual Expenditures:
$6,790,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31