Caltrans Logo

Fresno Track Extension

Description: Construct new track off the UPRR mainline, south of the BSNF crossing, in the UPRR railyard.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 17
Congressional District
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
BRIAN SCHMIDT (209) 944-6241   BRIAN@ACERAIL.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $6 $6
PTMISEA-99313
$2,034 $0 $2,034
Non-bond Funding
State/Federal*
$2,951 $-2,951 $0
Local**
$301 $199 $500
 
Total**** $5,287 $-2,747 $2,540

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,383 $-891 $7,491 $7,491 $7,491 $0
 
Total* $5,287 $-2,747 $2,540 $2,540 $2,540 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2008 

03/31/2008 
 

 
01/01/2008 

03/31/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/01/2008 

09/30/2009 
 

08/26/2011 
03/01/2009 

12/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2010 

09/30/2010 
09/03/2013 

09/03/2013 
08/30/2013 

12/15/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5

Bond Funding Cost
Adopted:
$2,034,061
Current Approved:
$2,034,061
Actual Expenditures:
$2,034,061

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31