Caltrans Logo

Timed Fill Compressed Natural Gas Bus Fueling Sta.

Description: CNG Fueling Station

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Turlock
Zip Code 95380
 
Senate District
12
Assembly District 26
Congressional District 19
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability (percent)        
Reduced Operating/Maintenance Cost        
Useful Life (years)  20      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
City of Turlock Roger Fall (209) 668-5520   rfall@turlock.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $7 $7
PTMISEA-99313
$315 $-43 $273
Non-bond Funding
 
Total**** $315 $-36 $280

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$35 $0 $35 $35 $35 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$281 $-36 $245 $245 $245 $0
 
Total* $315 $-36 $280 $280 $280 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2008 

07/01/2008 
 

 
04/01/2008 

07/01/2008 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2008 

12/01/2008 
04/21/2010 

04/21/2010 
09/09/2009 

07/20/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
12/01/2008 

02/28/2009 
03/09/2011 

09/29/2011 
12/14/2010 

09/30/2011 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability (percent)
Reduced Operating/Maintenance Cost
Useful Life (years) 20

Bond Funding Cost
Adopted:
$315,495
Current Approved:
$272,964
Actual Expenditures:
$272,964

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31