Tehema County Bus Purchase and Rehab

Description: Purchased 4 glaval titan buses, rehabitated 2 transit buses and installed 19 bus stop shelters

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tehama
City Gerber
Zip Code 96035
 
Senate District
02
Assembly District 02
Congressional District
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase in Ridership (percent)        
Increased Ridership      16  
Number of Buses Purchased for Replacment  2      
Number of Buses Rehabed  2      
Reduced Operating/Maintenance Cost        
Useful Life (years)  12      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
Tehama County Transportation Commission Barbara O'Keeffe (530) 385-1462 X3017   bokeeffe@tcpw.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $14 $14
PTMISEA-99313
$494 $0 $494
Non-bond Funding
Local**
$0 $0 $0
 
Total**** $494 $14 $508

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$494 $14 $508 $508 $508 $0
 
Total* $494 $14 $508 $508 $508 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/30/2008 

06/30/2009 
04/14/2010 

04/14/2010 
03/12/2009 

09/12/2009 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
09/02/2009 

09/02/2009 
12/01/2009 

12/31/2009 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase in Ridership (percent)
Increased Ridership 16
Number of Buses Purchased for Replacment 2
Number of Buses Rehabed 2
Reduced Operating/Maintenance Cost
Useful Life (years) 12

Bond Funding Cost
Adopted:
$493,732
Current Approved:
$493,732
Actual Expenditures:
$493,732

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31