ACE Station Improvements

Description: Project is to extend three Altamont Commuter Express stations to accomadate larger tain-sets

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
09, 10
Assembly District 15, 18
Congressional District 10, 11
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  30      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT TODD (510) 350-2315   MTODD@ACCMA.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99314
$283 $-79 $204
Non-bond Funding
Local**
$3,200 $0 $3,200
 
Total**** $3,483 $-79 $3,404

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$483 $-79 $404 $404 $404 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,000 $0 $3,000 $0 $0 $3,000
 
Total* $3,483 $-79 $3,404 $404 $404 $3,000

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2008 

02/01/2009 
 

03/06/2012 
08/01/2008 

05/31/2010 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2009 

10/01/2009 
11/15/2011 

11/15/2011 
09/01/2011 

12/31/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 30

Bond Funding Cost
Adopted:
$283,155
Current Approved:
$203,926
Actual Expenditures:
$203,926

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31