Caltrans Logo

Barstow Bus Stop Amenities

Description: Purchase and installation of 3 benches, pads, trash cans, signage, solar lights, and other amenities.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Bernardino
City Hesperia
Zip Code 92345
 
Senate District
18
Assembly District 33
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  1    2  
Increased Ridership  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KEVIN KANE (760) 948-4330   KKANE@VVTA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$5 $0 $5
PTMISEA-99313
$9 $0 $9
Non-bond Funding
 
Total**** $14 $0 $14

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$14 $0 $14 $14 $14 $0
 
Total* $14 $0 $14 $14 $14 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2014 

03/31/2015 
 

 
12/31/2014 

03/31/2015 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2015 

08/31/2015 
 

10/22/2015 
06/30/2015 

08/15/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 1 2
Increased Ridership 1

Bond Funding Cost
Adopted:
$14,314
Current Approved:
$9,166
Actual Expenditures:
$9,166

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31