Caltrans Logo

Passenger Amenities

Description: Purchase and installation of bus shelters and other passenger amenities to provide riders with a safe place to wait for buses

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Riverside
City Beaumont
Zip Code 92223
 
Senate District
37
Assembly District 65
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  50    50  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ELIZABETH URTIAGA (951) 769-8520   EURTIAGA@CI.BEAUMONT.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99313
$38 $99 $137
PTMISEA-99314
$7 $4 $11
Non-bond Funding
 
Total**** $45 $104 $149

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$45 $104 $149 $149 $149 $0
 
Total* $45 $104 $149 $149 $149 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
50   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
100   

 


Begin Construction Phase

End Construction Phase
11/01/2009 

12/01/2009 
09/13/2013 

09/13/2013 
01/15/2013 

02/15/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2010 

03/01/2010 
09/13/2013 

09/13/2013 
11/01/2013 

12/31/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 50 50

Bond Funding Cost
Adopted:
$45,304
Current Approved:
$148,181
Actual Expenditures:
$148,181

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31