Purchase Bus Lift and R134 A/C Machine

Description: Purchase one bus lift with accessories and one R134 A/C machine for maintenance at central garage

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Taft
Zip Code 93268
 
Senate District
32
Assembly District 18
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TERESA STATLER (661) 763-1350   TSTATLER@CITYOFTAFT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$2 $0 $2
PTMISEA-99314
$18 $0 $18
Non-bond Funding
Local**
$0 $1 $1
 
Total**** $20 $1 $20

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$20 $1 $20 $20 $20 $0
 
Total* $20 $1 $20 $20 $20 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/20/2010 

09/24/2010 
10/22/2015 

10/22/2015 
03/01/2011 

07/28/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
11/30/2010 

12/31/2010 
10/22/2015 

10/22/2015 
01/31/2015 

03/31/2015 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$19,514
Current Approved:
$19,514
Actual Expenditures:
$19,514

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31