Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Universal Fare Technology Program |
Description: Develop & implement a regional fare collection systeym
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Placer |
City | Roseville, Ca |
Zip Code | 95678 |
Senate District |
01 |
Assembly District | 04 |
Congressional District | |
Caltrans District |
03 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 2 | |
Increased Ridership | 3 | |
Reduced Operating/Maintenance Cost | 4 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
MICHAEL WIXON | (916) 774-5293 | MWIXON@ROSEVILLE.CA.US |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $2 | $2 | ||||
PTMISEA-99313 |
$256 | $0 | $256 | ||||
PTMISEA-99314 |
$32 | $0 | $32 | ||||
Non-bond Funding | |||||||
Local** |
$0 | $99 | $99 | ||||
Total**** | $288 | $101 | $389 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$288 | $101 | $389 | $389 | $389 | $0 | |
Total* | $288 | $101 | $389 | $389 | $389 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2009 12/01/2010 |
08/19/2011 |
09/01/2009 08/31/2011 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2011 12/30/2011 |
|
03/01/2011 12/30/2011 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
09/01/2011 12/01/2011 |
08/19/2011 03/19/2012 |
06/01/2012 06/30/2012 |
100 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 2 | |
Increased Ridership | 3 | |
Reduced Operating/Maintenance Cost | 4 |
Bond Funding Cost | |
---|---|
Adopted: |
$288,418 |
Current Approved: |
$288,418 |
Actual Expenditures: |
$288,418 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31