Caltrans Logo

Universal Fare Technology Program

Description: Develop & implement a regional fare collection systeym

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Roseville, Ca
Zip Code 95678
 
Senate District
01
Assembly District 04
Congressional District
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2      
Increased Ridership  3      
Reduced Operating/Maintenance Cost  4      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MICHAEL WIXON (916) 774-5293   MWIXON@ROSEVILLE.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$256 $0 $256
PTMISEA-99314
$32 $0 $32
Non-bond Funding
Local**
$0 $99 $99
 
Total**** $288 $101 $389

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$288 $101 $389 $389 $389 $0
 
Total* $288 $101 $389 $389 $389 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2009 

12/01/2010 
 

08/19/2011 
09/01/2009 

08/31/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2011 

12/30/2011 
 

 
03/01/2011 

12/30/2011 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2011 

12/01/2011 
08/19/2011 

03/19/2012 
06/01/2012 

06/30/2012 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2
Increased Ridership 3
Reduced Operating/Maintenance Cost 4

Bond Funding Cost
Adopted:
$288,418
Current Approved:
$288,418
Actual Expenditures:
$288,418

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31