Description: Purchase security cameras for bus security & scanner for analysis & maintenance for bus diesel engines

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Folsom, Ca
Zip Code 95630
 
Senate District
02
Assembly District 05
Congressional District 03
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  4    4  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KENT M. GARY (916) 355-8368   KGARY@FOLSOM.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99314
$34 $0 $34
Non-bond Funding
Local**
$0 $0 $0
 
Total**** $34 $0 $34

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$34 $0 $34 $34 $34 $-0
 
Total* $34 $0 $34 $34 $34 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2010 

04/30/2011 
 

 
12/31/2010 

04/30/2011 
 

 


Begin Closeout Phase

End Closeout Phase
05/01/2011 

07/01/2011 
 

 
05/01/2011 

07/01/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 4 4

Bond Funding Cost
Adopted:
$34,201
Current Approved:
$34,226
Actual Expenditures:
$34,226

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31