Mobile Data Computers for Dial-A-Ride (DAR)

Description: Purchase & Install Mobile Data Computers for Dial-A-Ride (DAR)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Merced
Zip Code 95340
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
ROD GHEARING (209) 385-7600   RGHEARING@CO.MERCED.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $3 $3
PTMISEA-99313
$137 $0 $137
Non-bond Funding
Local**
$0 $27 $27
 
Total**** $137 $31 $168

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$137 $31 $168 $168 $168 $0
 
Total* $137 $31 $168 $168 $168 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2010 

06/01/2010 
03/07/2014 

03/15/2016 
09/01/2013 

10/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2010 

07/30/2010 
03/15/2016 

03/15/2016 
09/15/2015 

10/15/2015 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5

Bond Funding Cost
Adopted:
$137,240
Current Approved:
$137,240
Actual Expenditures:
$137,240

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31