Securing Corporation Yard/Bus Storage Facility

Description: To contruct a block wall that will enclose the corp yard for bus storage

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Mcfarland
Zip Code 93250
 
Senate District
18
Assembly District 30
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DENNIS MCNAMARA (661) 792-3091   DMCNAMARA@MCFARLANDCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $2 $2
PTMISEA-99313
$58 $0 $58
PTMISEA-99314
$1 $0 $1
Non-bond Funding
Local**
$0 $11 $11
 
Total**** $58 $13 $72

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $-0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$58 $14 $72 $72 $72 $0
 
Total* $58 $13 $72 $72 $72 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/2011 

11/01/2011 
04/14/2014 

04/14/2014 
10/01/2011 

10/01/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2011 

01/31/2012 
04/14/2014 

04/14/2014 
11/01/2011 

11/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2012 

05/01/2012 
04/14/2014 

04/14/2014 
06/01/2012 

10/16/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2012 

07/31/2012 
04/14/2014 

04/14/2014 
10/16/2012 

10/15/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 5

Bond Funding Cost
Adopted:
$58,151
Current Approved:
$58,151
Actual Expenditures:
$58,151

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31