Vacaville Bus Shelters

Description: Project is to install 10 new bus shelters with standard ammenities

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Solano
City Fairfield
Zip Code 94533
 
Senate District
05
Assembly District 08
Congressional District 10
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    19  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GEORG K. FINK (707) 428-7768   GFINK@CI.FAIRFIELD.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$110 $0 $110
Non-bond Funding
Local**
$27 $0 $27
 
Total**** $137 $0 $137

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$137 $0 $137 $137 $137 $0
 
Total* $137 $0 $137 $137 $137 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
04/01/2009 

05/01/2009 
06/10/2010 

06/10/2010 
01/01/2010 

02/04/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
05/01/2009 

08/01/2009 
08/22/2012 

08/22/2012 
06/30/2012 

06/30/2012 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 19

Bond Funding Cost
Adopted:
$109,800
Current Approved:
$109,800
Actual Expenditures:
$109,800

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31