Randolph/Farallones/Orizaba/ Transit Access Pedestrian Safety Project |
Description: Project is to provide Improvements to pedestrian access to transit in San Francisco Oceanview neighborhood
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Francisco |
City | San Francisco, Ca |
Zip Code | 94103 |
Senate District |
08 |
Assembly District | 12 |
Congressional District | 08 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
JOEL C. GOLDBERG | (415) 701-4499 | JOEL.GOLDBERG@SFMTA.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $96 | $96 | ||||
PTMISEA-99313 |
$480 | $-101 | $379 | ||||
Non-bond Funding | |||||||
Local** |
$120 | $-85 | $35 | ||||
Total**** | $600 | $-89 | $511 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $75 | $75 | $75 | $75 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$600 | $-164 | $436 | $436 | $436 | $0 | |
Total* | $600 | $-89 | $511 | $511 | $511 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
01/31/2009 03/31/2009 |
04/12/2011 04/12/2011 |
12/01/2009 06/30/2011 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/31/2009 05/31/2009 |
04/12/2011 09/03/2014 |
06/30/2011 07/31/2014 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/31/2010 02/28/2012 |
09/03/2014 03/10/2015 |
10/01/2014 03/30/2015 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
03/30/2012 09/01/2012 |
07/15/2015 07/15/2015 |
09/01/2015 12/31/2015 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 |
Bond Funding Cost | |
---|---|
Adopted: |
$480,000 |
Current Approved: |
$379,490 |
Actual Expenditures: |
$379,490 |
Status as of December 31, 2023.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31