Caltrans Logo

Metro Express/Airport Way BRT

Description: Establish a new Bus Rapid Transit (BRT) between downtown Stockton and the Stockton Metropolitan Airport.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05, 14
Assembly District 15, 16, 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  50    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA DEMARTINO (209) 948-5566 X613   DDEMARTINO@SANJOAQUINRTD.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$400 $0 $400
PTMISEA-99314
$386 $0 $386
Non-bond Funding
State/Federal*
$110 $5,519 $5,629
Local**
$2,809 $-2,144 $665
 
Total**** $3,705 $3,375 $7,080

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$468 $-468 $0 $0 $0 $0
Design(PS&E)
$343 $-343 $0 $0 $0 $0
Right of Way
$491 $-491 $0 $0 $0 $0
Construction
$2,403 $4,677 $7,080 $7,080 $7,080 $0
 
Total* $3,705 $3,375 $7,080 $7,080 $7,080 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
03/01/2009 

04/01/2009 
 

 
03/01/2009 

04/01/2009 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2009 

05/31/2010 
 

 
04/01/2009 

05/31/2010 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2009 

04/30/2010 
08/26/2011 

08/26/2011 
07/31/2010 

09/30/2010 
100   

 


Begin Closeout Phase

End Closeout Phase
05/31/2010 

08/31/2010 
 

 
09/30/2011 

12/31/2011 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 50 10

Bond Funding Cost
Adopted:
$786,057
Current Approved:
$786,057
Actual Expenditures:
$786,057

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31