Caltrans Logo

Rocklin Park & Ride Expansion

Description: Expand existing parking lot & add 20+ parking spaces

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Placer
City Rocklin, Ca
Zip Code 95677
 
Senate District
04
Assembly District 04
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability        
Increased Ridership  20      
Reduced Emissions  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
LARRY WING (916) 625-5145   LARRY.WING@ROCKLIN.CA.US
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$1,219 $-1,004 $215
Non-bond Funding
Local**
$895 $-895 $0
 
Total**** $2,115 $-1,899 $215

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$20 $-20 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,095 $-1,879 $215 $215 $215 $0
 
Total* $2,115 $-1,899 $215 $215 $215 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2010 

02/01/2011 
03/14/2012 

03/14/2012 
10/01/2011 

01/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2010 

02/01/2011 
 

 
06/01/2010 

02/01/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
02/01/2011 

08/01/2011 
03/14/2012 

03/14/2012 
11/01/2011 

03/01/2012 
 

 


Begin Construction Phase

End Construction Phase
04/01/2012 

11/01/2012 
 

 
04/01/2012 

11/01/2012 
 

 


Begin Closeout Phase

End Closeout Phase
12/01/2012 

06/30/2013 
 

03/14/2012 
12/01/2012 

01/01/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability
Increased Ridership 20
Reduced Emissions 5

Bond Funding Cost
Adopted:
$1,219,313
Current Approved:
$215,164
Actual Expenditures:
$215,164

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31