TO Transit - Replacement Buses (2)

Description: Purchase 3 40-foot, 32-passenger, fully ADA compliant CNG buses, 2 support vehicles & 5 fareboxes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 37
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    25  
Reduced Emissions  5    10  
Reduced Operating/Maintenance Cost  20    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
PETER DEHAAN (805) 642-1591 X106   PDEHAAN@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $36 $36
PTMISEA-99313
$572 $30 $601
PTMISEA-99314
$0 $190 $190
Non-bond Funding
State/Federal*
$387 $365 $752
Local**
$0 $72 $72
 
Total**** $959 $693 $1,652

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$959 $693 $1,652 $1,652 $1,652 $0
 
Total* $959 $693 $1,652 $1,652 $1,652 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
09/01/2010 

12/31/2010 
 

09/16/2013 
09/01/2010 

07/31/2013 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2011 

07/01/2011 
09/05/2017 

09/05/2017 
03/01/2017 

06/27/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2013 

07/01/2013 
09/05/2018 

02/24/2020 
01/31/2019 

06/30/2019 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 25
Reduced Emissions 5 10
Reduced Operating/Maintenance Cost 20 20

Bond Funding Cost
Adopted:
$571,601
Current Approved:
$791,290
Actual Expenditures:
$791,290

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31