Caltrans Logo

Brawley Transit Transfer Terminal

Description: Transit transfer station in the City of Brawley

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City El Centro
Zip Code 92243
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  25      
Increased Ridership  15    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHI WILLIAMS (760) 592-4494   KATHIWILLIAMS@IMPERIALCTC.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $8 $8
PTMISEA-99313
$511 $0 $511
Non-bond Funding
State/Federal*
$300 $133 $433
 
Total**** $811 $141 $952

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,092 $141 $1,233 $1,233 $1,233 $0
 
Total* $811 $141 $952 $952 $952 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/31/2011 

09/30/2011 
 

 
03/31/2011 

09/30/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
03/01/2011 

07/31/2011 
 

 
03/01/2011 

07/31/2011 
100   

 


Begin Construction Phase

End Construction Phase
11/01/2011 

06/01/2012 
04/23/2013 

04/23/2013 
01/31/2013 

06/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
06/01/2012 

07/31/2012 
04/23/2013 

04/23/2013 
06/02/2013 

07/31/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 25
Increased Ridership 15 2

Bond Funding Cost
Adopted:
$511,290
Current Approved:
$511,290
Actual Expenditures:
$511,290

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31