Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Environmental Justice Access to BART |
Description: 268 space bike racks at downtown Berkeley BART Station, 24 electronic bike lockers at North Berkeley BART Station
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Alameda |
City | Oakland |
Zip Code | 94604 |
Senate District |
09 |
Assembly District | 14 |
Congressional District | 10 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 0 | 1 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
STEVE BEROLDO | (510) 464-6158 | SBEROLDO@BART.GOV |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-99313 |
$225 | $0 | $225 | ||||
Non-bond Funding | |||||||
State/Federal* |
$142 | $3,584 | $3,726 | ||||
Local** |
$497 | $8,586 | $9,082 | ||||
Total**** | $864 | $12,170 | $13,033 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$79 | $-23 | $56 | $56 | $56 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$785 | $12,192 | $12,977 | $4,555 | $4,555 | $8,422 | |
Total* | $864 | $12,170 | $13,033 | $4,611 | $4,611 | $8,422 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2009 03/31/2010 |
|
01/01/2009 03/31/2010 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
07/01/2010 03/31/2011 |
02/21/2023 08/12/2021 |
08/01/2018 08/01/2021 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2011 12/31/2013 |
02/21/2023 02/21/2023 |
09/01/2021 12/30/2022 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 0 | 1 |
Bond Funding Cost | |
---|---|
Adopted: |
$224,749 |
Current Approved: |
$224,749 |
Actual Expenditures: |
$224,749 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31