Caltrans Logo

Bus Stop Improvements

Description: Improvement of 50 to 60 bus stops throughout San Mateo County

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Mateo
City San Carlos
Zip Code 94070
 
Senate District
08, 11
Assembly District 12, 19, 21
Congressional District 12, 14
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Reduced Operating/Maintenance Cost  40    40  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
SUNA MULLINS (650) 508-6490   MULLINSS@SAMTRANS.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$197 $-41 $156
Non-bond Funding
Local**
$0 $31 $31
 
Total**** $197 $-10 $187

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$197 $-10 $187 $187 $187 $0
 
Total* $197 $-10 $187 $187 $187 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2011 

06/30/2013 
02/24/2017 

03/01/2019 
09/30/2017 

04/30/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
06/30/2013 

09/30/2013 
03/01/2019 

03/01/2019 
05/31/2019 

09/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Operating/Maintenance Cost 40 40

Bond Funding Cost
Adopted:
$196,867
Current Approved:
$156,028
Actual Expenditures:
$156,028

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31