Caltrans Logo

Engine/Parts Cleaner Installation

Description: Procurement and installation of steam cleaner, and recovery system/ cabinet for maintenance of parts, roof over cleaner

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Diamond Springs
Zip Code 95619
 
Senate District
01
Assembly District 04, 10
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Reduced Operating/Maintenance Cost  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MATT MAUK (530) 642-5383   MMAUK@ELDORADOTRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$200 $0 $200
Non-bond Funding
 
Total**** $200 $0 $200

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $0 $200 $200 $200 $0
 
Total* $200 $0 $200 $200 $200 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
09/11/2012 

03/07/2013 
01/01/2012 

03/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
03/01/2012 

04/30/2012 
09/11/2012 

03/07/2013 
03/01/2013 

04/30/2013 
50   

 


Begin Closeout Phase

End Closeout Phase
04/30/2012 

06/30/2012 
09/11/2012 

03/07/2013 
04/30/2013 

06/30/2013 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Reduced Operating/Maintenance Cost 3 3

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$200,000
Actual Expenditures:
$200,000

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31