CNG Bus Replacement (15 Buses)

Description: Purchase 15 new buses to replace 2002 Orion Buses that have accumulated 500,000 miles as the manufacturer no longer provides replacement parts. New buses to provide better emission perfromance.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
30
Assembly District 16
Congressional District 20
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  100    100  
Increased Ridership  5      
Reduced Emissions  20      
Reduced Operating/Maintenance Cost  25      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEVE WOODS (661) 861-2191   SWOODS@GETBUS.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $17 $17
PTMISEA-99313
$6,783 $-1,558 $5,226
PTMISEA-99314
$706 $0 $706
Non-bond Funding
State/Federal*
$0 $1,734 $1,734
 
Total**** $7,489 $193 $7,682

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$7,489 $193 $7,682 $7,682 $7,682 $0
 
Total* $7,489 $193 $7,682 $7,682 $7,682 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
10/18/2011 

11/01/2011 
 

06/26/2014 
10/18/2011 

02/05/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
09/01/2012 

11/01/2012 
06/26/2014 

06/26/2014 
02/21/2014 

04/13/2014 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 100 100
Increased Ridership 5
Reduced Emissions 20
Reduced Operating/Maintenance Cost 25

Bond Funding Cost
Adopted:
$7,489,192
Current Approved:
$5,931,664
Actual Expenditures:
$5,931,664

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31