Modoc Transportation Center

Description: rehabilitation and modernization project on a new transportation center with bus yard including garage space

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Modoc
City Alturas
Zip Code 96101
 
Senate District
01
Assembly District 02
Congressional District 04
 
Caltrans District
02
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  34    34  
Increased Ridership  33      
Reduced Operating/Maintenance Cost  33      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CINDY IMBACH (530) 233-6410   CIMBACH@FRONTIERNET.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $0 $0
PTMISEA-99313
$243 $107 $351
Non-bond Funding
State/Federal*
$8 $932 $940
Local**
$0 $273 $273
 
Total**** $251 $1,312 $1,564

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $150 $150 $150 $150 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $327 $327 $327 $327 $0
Construction
$251 $835 $1,087 $1,087 $1,087 $0
 
Total* $251 $1,312 $1,564 $1,564 $1,564 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2011 

06/30/2014 
03/05/2014 

03/05/2014 
10/01/2012 

07/31/2013 
 

 


Begin Closeout Phase

End Closeout Phase
06/30/2014 

06/30/2015 
03/05/2014 

03/05/2014 
08/01/2013 

01/30/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 34 34
Increased Ridership 33
Reduced Operating/Maintenance Cost 33

Bond Funding Cost
Adopted:
$243,373
Current Approved:
$350,606
Actual Expenditures:
$350,606

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31