Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
30 Bus Replacement |
Description: Purchase 30 diesel/electric hybrid powered, low floor, 44 passenger buses
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Contra Costa |
City | Antioch |
Zip Code | 94509 |
Senate District |
07 |
Assembly District | 11, 15 |
Congressional District | 07, 10 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | |
Reduced Emissions | 25 | 25 |
Reduced Operating/Maintenance Cost | 10 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
TOM HARAIS | (925) 754-6622 | THARAIS@ECCTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $14 | $14 | ||||
PTMISEA-99313 |
$1,861 | $0 | $1,861 | ||||
PTMISEA-99314 |
$1,061 | $0 | $1,061 | ||||
Non-bond Funding | |||||||
State/Federal* |
$14,354 | $-6,071 | $8,284 | ||||
Local** |
$805 | $172 | $977 | ||||
Total**** | $18,081 | $-5,884 | $12,197 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$14,720 | $-14,720 | $0 | $0 | $0 | $0 | |
Construction |
$3,361 | $8,836 | $12,197 | $12,197 | $12,197 | $0 | |
Total* | $18,081 | $-5,884 | $12,197 | $12,197 | $12,197 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/28/2011 11/16/2011 |
08/23/2012 |
09/28/2011 02/27/2012 |
0 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
12/01/2012 06/30/2013 |
08/28/2013 08/28/2013 |
06/01/2013 06/30/2013 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 25 | |
Reduced Emissions | 25 | 25 |
Reduced Operating/Maintenance Cost | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$2,922,016 |
Current Approved: |
$2,922,016 |
Actual Expenditures: |
$2,922,016 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31