City of Manteca Multimodal Station Construction

Description: Constructing a multimodal transit center in the downtown area of Manteca

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05
Assembly District 26
Congressional District 11
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability      50  
Increased Ridership  5    5  
Reduced Emissions      15  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
AARON HOYT (209) 235-0450   AHOYT@SJCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$1,500 $-186 $1,314
Non-bond Funding
State/Federal*
$4,141 $2,474 $6,615
Local**
$956 $-580 $376
 
Total**** $6,597 $1,709 $8,306

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$380 $-380 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$6,597 $1,709 $8,306 $8,306 $8,306 $0
 
Total* $6,597 $1,709 $8,306 $8,306 $8,306 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

09/14/2010 
 

 
 

09/14/2010 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/18/2011 

06/10/2011 
 

09/07/2012 
01/18/2011 

05/20/2013 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/19/2011 

10/16/2012 
09/07/2012 

05/19/2020 
06/04/2012 

05/31/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
10/16/2012 

12/14/2012 
05/19/2020 

05/19/2020 
05/31/2011 

06/30/2019 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 50
Increased Ridership 5 5
Reduced Emissions 15

Bond Funding Cost
Adopted:
$1,500,000
Current Approved:
$1,314,413
Actual Expenditures:
$1,314,413

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31