Caltrans Logo

Maintenance Equipment

Description: Purchase associated capital maintenance/shop equipment, engine replacements and component rebuilds

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code 95202
 
Senate District
05, 14
Assembly District 10, 15, 17, 26
Congressional District 11, 18
 
Caltrans District
10
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    18  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
DONNA DEMARTINO (209) 948-5566   DDMARTINO@SANJOAQUINRTD.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $13 $13
PTMISEA-99314
$1,266 $0 $1,266
Non-bond Funding
 
Total**** $1,266 $13 $1,279

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$1,266 $13 $1,279 $1,279 $1,279 $0
 
Total* $1,266 $13 $1,279 $1,279 $1,279 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
01/01/2012 

06/30/2012 
03/07/2019 

03/07/2019 
04/13/2012 

09/01/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2012 

10/01/2012 
03/07/2019 

03/07/2019 
12/01/2018 

12/31/2018 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 18

Bond Funding Cost
Adopted:
$1,265,893
Current Approved:
$1,265,893
Actual Expenditures:
$1,265,893

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31