Caltrans Logo

Glenn Ride Vehicle Replacement

Description: To purchase two new 40 ft. heavy duty transit buses with a passenger capacity of 39 persons.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Glenn
City Willows
Zip Code 95988
 
Senate District
02
Assembly District 04
Congressional District 02
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    3  
Reduced Emissions  15    5  
Reduced Operating/Maintenance Cost  40    28  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
John Linhart (530) 934-6541   jlinhart@countyofglenn.net
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-99313
$561 $-15 $546
Non-bond Funding
State/Federal*
$300 $0 $300
 
Total**** $861 $-15 $846

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$861 $-15 $846 $846 $846 $0
 
Total* $861 $-15 $846 $846 $846 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2011 

10/01/2012 
 

 
07/01/2011 

10/01/2012 
100   

 


Begin Closeout Phase

End Closeout Phase
08/01/2012 

08/31/2012 
08/15/2012 

03/14/2013 
01/01/2013 

03/06/2013 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 3
Reduced Emissions 15 5
Reduced Operating/Maintenance Cost 40 28

Bond Funding Cost
Adopted:
$561,142
Current Approved:
$545,827
Actual Expenditures:
$545,827

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31