Caltrans Logo

Moorpark City Transit Vehicles (2 CNG Buses)

Description: Purchase of two replacement CNG buses.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
19
Assembly District 35
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10    10  
Increased Ridership  8    8  
Reduced Emissions  20    45  
Reduced Operating/Maintenance Cost  16    29  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEPHANIE YOUNG (805) 642-1591 X108   SYOUNG@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$774 $0 $774
Non-bond Funding
State/Federal*
$90 $0 $90
 
Total**** $864 $0 $864

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$864 $0 $864 $774 $774 $90
 
Total* $864 $0 $864 $774 $774 $90

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
07/01/2013 

07/01/2014 
08/28/2014 

09/21/2016 
10/01/2014 

01/19/2016 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

08/01/2014 
09/21/2016 

09/21/2016 
01/19/2016 

06/30/2016 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10 10
Increased Ridership 8 8
Reduced Emissions 20 45
Reduced Operating/Maintenance Cost 16 29

Bond Funding Cost
Adopted:
$774,000
Current Approved:
$774,000
Actual Expenditures:
$774,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31