Caltrans Logo

San Bernardino Downtown Passenger Rail Line Extension

Description: Extension of existing Metrolink rail ine approximately one mile east from from its current terminus to a new terminus proposed near the intersection of Rialto Ave and E Street.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
Project Location
County
San Bernardino
City San Bernardino
Zip Code 92410
 
Senate District
32
Assembly District 47
Congressional District
 
Caltrans District
08
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5    5  
Reduced Emissions  5    5  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
JUSTIN FORNELLI (909) 884-8276   JFORNELLI@SANBAG.CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $69 $69
PTMISEA-99313
$6,420 $0 $6,420
Non-bond Funding
State/Federal*
$40,166 $35,788 $75,954
Local**
$0 $27,117 $27,117
 
Total**** $46,586 $62,974 $109,560

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $15,551 $15,551 $0 $0 $15,551
Right of Way
$2,000 $12,195 $14,195 $0 $0 $14,195
Construction
$44,586 $35,229 $79,815 $6,420 $6,420 $73,395
 
Total* $46,586 $62,974 $109,560 $6,420 $6,420 $103,140

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2010 

10/01/2012 
 

 
02/01/2010 

10/01/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2011 

05/01/2012 
 

 
01/01/2011 

05/01/2012 
100   

 


Begin Right of Way Phase

End Right of Way Phase
11/01/2012 

12/01/2013 
 

10/20/2015 
11/01/2012 

06/01/2016 
100   

 


Begin Construction Phase

End Construction Phase
12/01/2013 

03/01/2016 
 

03/06/2016 
12/01/2013 

08/01/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2016 

10/01/2016 
09/30/2017 

09/30/2018 
08/01/2017 

12/01/2017 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5 5
Reduced Emissions 5 5

Bond Funding Cost
Adopted:
$6,419,844
Current Approved:
$6,419,844
Actual Expenditures:
$6,419,844

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31