State Route 4 (West Crosstown Freeway Extension) Phase I

Description: Construct Freeway Extension

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Stockton
Zip Code
 
Senate District
05
Assembly District 10
Congressional District 11
 
Caltrans District
10
 
 
County/State Route San Joaquin 4
Postmile Begin/End 14.4 14.8
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  3.0    3  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
San Joaquin Council of Governments Kevin Sheridan (209) 468-3913   sheridan@sjcog.org
Design (PS&E) Phase
San Joaquin Council of Governments Kevin Sheridan (209) 468-3913   sheridan@sjcog.org
Right of Way Phase
Caltrans Scott Guidi (209) 948-7829   scott.guidi@dot.ca.gov
Construction Phase
San Joaquin Council of Governments Kevin Sheridan (209) 468-3913   sheridan@sjcog.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
TCIF
$96,820 $-27,362 $69,458
Non-bond Funding
Local**
$96,820 $-27,962 $68,858
 
Total**** $193,640 $-55,324 $138,316

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$4,000 $0 $4,000 $4,000 $0 $4,000
Design(PS&E)
$10,500 $-100 $10,400 $10,400 $0 $10,400
Right of Way
$44,600 $0 $44,600 $44,600 $0 $44,600
Construction
$134,540 $-55,224 $79,316 $67,967 $0 $79,316
 
Total* $193,640 $-55,324 $138,316 $126,967 $0 $138,316

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2008 

11/01/2010 
 

 
05/01/2008 

11/01/2010 
100  05/01/2008 

11/01/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2010 

02/01/2013 
03/28/2012 

03/28/2012 
10/01/2010 

06/01/2013 
100  10/01/2010 

06/01/2013 


Begin Right of Way Phase

End Right of Way Phase
08/01/2010 

01/01/2013 
03/28/2012 

03/28/2012 
10/01/2010 

05/01/2013 
100  10/01/2010 

05/01/2013 


Begin Construction Phase

End Construction Phase
06/01/2013 

06/01/2016 
03/28/2012 

03/28/2012 
11/01/2013 

12/01/2016 
100  12/16/2013 

08/31/2017 
-1 

-9 
Begin Closeout Phase

End Closeout Phase
08/01/2016 

08/01/2017 
03/28/2012 

 
12/01/2016 

12/01/2017 
50  08/31/2017 

12/07/2017 
-9 

????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 3.0 3

Bond Funding Cost
Adopted:
$96,820,000
Current Approved:
$69,458,000
Actual Expenditures:
$55,783,471

 

Status as of December 31, 2023.