Bus Stop Improvement Plan Upgrades

Description: Improve four bus stops by installing ADA ramps, concrete bus pads, bus shelters, benches, trash cans, route maps, bus stop signs, crosswalks and red curbs.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
18
Assembly District 12
Congressional District 17
 
Caltrans District
05
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  5      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
REGINA VALENTINE (831) 637-7665   REGINA@SANBENITOCOG.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$200 $-168 $32
Non-bond Funding
 
Total**** $200 $-168 $32

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$200 $-168 $32 $32 $32 $0
 
Total* $200 $-168 $32 $32 $32 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2018 

10/01/2018 
 

08/10/2020 
07/01/2018 

12/01/2020 
50   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2018 

07/30/2018 
 

08/10/2020 
07/01/2018 

12/01/2020 
100   

 


Begin Right of Way Phase

End Right of Way Phase
10/01/2018 

12/01/2018 
 

04/14/2021 
10/01/2019 

06/01/2022 
 

 


Begin Construction Phase

End Construction Phase
05/01/2019 

08/01/2019 
04/14/2021 

04/19/2023 
07/01/2022 

12/01/2023 
100   

 


Begin Closeout Phase

End Closeout Phase
10/01/2019 

12/01/2019 
04/19/2023 

04/19/2023 
12/01/2023 

12/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 5

Bond Funding Cost
Adopted:
$200,000
Current Approved:
$31,833
Actual Expenditures:
$31,833

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31