Caltrans Logo

Crenshaw/LAX Transit Corridor

Description: 8.5-mile LRT extension from Crenshaw/Exposition Blvds that allows for the Expo LRT line to connect with the Green Line at the Aviation/LAX Station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
25, 26
Assembly District 47, 51, 53
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GLADYS LOWE (213) 922-2459   LOWEG@METRO.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $433 $433
PTMISEA-99313
$0 $116,517 $116,517
PTMISEA-99314
$12,000 $0 $12,000
Non-bond Funding
State/Federal*
$134,563 $77,443 $212,006
Local**
$1,413,058 $231,557 $1,644,615
 
Total**** $1,559,621 $425,950 $1,985,571

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$50,000 $-24,629 $25,371 $25,549 $25,549 $-178
Design(PS&E)
$0 $29,798 $29,798 $29,306 $29,306 $492
Right of Way
$98,732 $-6,106 $92,626 $138,235 $138,235 $-45,609
Construction
$1,410,889 $426,887 $1,837,777 $1,890,288 $1,890,288 $-52,511
 
Total* $1,559,621 $425,950 $1,985,571 $2,083,378 $2,083,378 $-97,807

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2007 

01/30/2012 
08/30/2013 

08/30/2013 
06/29/2007 

12/30/2011 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/02/2013 

12/31/2014 
08/30/2013 

08/30/2013 
12/31/2011 

07/31/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
10/04/2011 

10/03/2013 
04/14/2022 

04/14/2022 
09/29/2011 

12/31/2021 
100   

 


Begin Construction Phase

End Construction Phase
07/27/2013 

07/27/2018 
04/14/2022 

08/18/2020 
07/13/2013 

10/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
10/25/2018 

10/30/2020 
04/14/2022 

04/14/2022 
10/02/2022 

10/31/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 2 2

Bond Funding Cost
Adopted:
$12,000,000
Current Approved:
$128,516,870
Actual Expenditures:
$128,516,870

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31