Berkeley BART Plaza/Transit Area Improvements

Description: Improvements to BART main & secondary entrances, new bus shelter, public plaza resurfacing, landscaping, lighting, wayfinding, curb ramps, bike parking

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
13, 16
Assembly District 03, 09
Congressional District 07, 08, 09, 10, 11, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  1    1  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
TIAN FENG (510) 464-6549   TFENG@BART.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $79 $79
PTMISEA-99314
$3,726 $0 $3,726
Non-bond Funding
State/Federal*
$0 $4,776 $4,776
Local**
$0 $6,176 $6,176
 
Total**** $3,726 $11,031 $14,757

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,726 $11,031 $14,757 $14,757 $14,757 $0
 
Total* $3,726 $11,031 $14,757 $14,757 $14,757 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/01/2003 

07/15/2015 
 

 
11/01/2003 

07/15/2015 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2013 

07/20/2015 
 

 
12/01/2013 

07/20/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/01/2015 

02/28/2017 
 

09/16/2019 
12/01/2015 

12/28/2018 
100   

 


Begin Closeout Phase

End Closeout Phase
03/01/2017 

07/30/2017 
02/27/2020 

02/27/2020 
12/31/2019 

06/30/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 1 1

Bond Funding Cost
Adopted:
$3,726,000
Current Approved:
$3,726,000
Actual Expenditures:
$3,726,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31