Regional Connector Transit Corridor |
Description: 2 mile light rail project that will provide a seamless connection with the Metro Gold, Metro Blue, and Metro Expo light rail systems through downtown Los Angeles.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Los Angeles |
Zip Code | 90012 |
Senate District |
21, 22 |
Assembly District | 45, 46 |
Congressional District | |
Caltrans District |
07 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 6 | 6 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
KATHY BANH | (213) 922-7635 | BANHK@METRO.NET |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$63 | $0 | $63 | ||||
PTMISEA-99313 |
$23,376 | $29,310 | $52,686 | ||||
PTMISEA-99314 |
$126,124 | $-43,710 | $82,414 | ||||
Non-bond Funding | |||||||
State/Federal* |
$848,800 | $14,374 | $863,174 | ||||
Local** |
$365,147 | $53,943 | $419,090 | ||||
Total**** | $1,363,510 | $53,917 | $1,417,427 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$56,868 | $-36,344 | $20,524 | $22,465 | $22,465 | $-1,941 | |
Design(PS&E) |
$0 | $43,594 | $43,594 | $43,978 | $43,978 | $-384 | |
Right of Way |
$116,360 | $-471 | $115,889 | $58,266 | $58,266 | $57,623 | |
Construction |
$1,190,282 | $47,138 | $1,237,420 | $1,518,304 | $1,518,304 | $-280,883 | |
Total* | $1,363,510 | $53,917 | $1,417,427 | $1,643,012 | $1,643,012 | $-225,586 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/01/2009 06/29/2012 |
|
02/01/2009 06/29/2012 |
100 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/30/2012 01/30/2015 |
07/09/2014 |
06/30/2012 12/07/2015 |
100 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2011 06/30/2014 |
08/18/2020 |
07/01/2011 07/31/2020 |
100 | |
0 0 |
Begin Construction Phase
End Construction Phase |
10/21/2013 01/29/2020 |
07/09/2014 03/06/2020 |
07/01/2014 04/01/2022 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/01/2020 02/28/2022 |
03/06/2020 03/06/2020 |
04/01/2022 06/30/2023 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increased Ridership | 6 | 6 |
Bond Funding Cost | |
---|---|
Adopted: |
$149,562,779 |
Current Approved: |
$135,100,000 |
Actual Expenditures: |
$135,100,000 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31