Caltrans Logo

Regional Connector Transit Corridor

Description: 2 mile light rail project that will provide a seamless connection with the Metro Gold, Metro Blue, and Metro Expo light rail systems through downtown Los Angeles.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Los Angeles
Zip Code 90012
 
Senate District
21, 22
Assembly District 45, 46
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  6    6  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATHY BANH (213) 922-7635   BANHK@METRO.NET
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$63 $0 $63
PTMISEA-99313
$23,376 $29,310 $52,686
PTMISEA-99314
$126,124 $-43,710 $82,414
Non-bond Funding
State/Federal*
$848,800 $14,374 $863,174
Local**
$365,147 $53,943 $419,090
 
Total**** $1,363,510 $53,917 $1,417,427

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$56,868 $-36,344 $20,524 $22,465 $22,465 $-1,941
Design(PS&E)
$0 $43,594 $43,594 $43,978 $43,978 $-384
Right of Way
$116,360 $-471 $115,889 $58,266 $58,266 $57,623
Construction
$1,190,282 $47,138 $1,237,420 $1,518,304 $1,518,304 $-280,883
 
Total* $1,363,510 $53,917 $1,417,427 $1,643,012 $1,643,012 $-225,586

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2009 

06/29/2012 
 

 
02/01/2009 

06/29/2012 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/30/2012 

01/30/2015 
 

07/09/2014 
06/30/2012 

12/07/2015 
100   

 


Begin Right of Way Phase

End Right of Way Phase
07/01/2011 

06/30/2014 
 

08/18/2020 
07/01/2011 

07/31/2020 
100   

 


Begin Construction Phase

End Construction Phase
10/21/2013 

01/29/2020 
07/09/2014 

03/06/2020 
07/01/2014 

04/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2020 

02/28/2022 
03/06/2020 

03/06/2020 
04/01/2022 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 6 6

Bond Funding Cost
Adopted:
$149,562,779
Current Approved:
$135,100,000
Actual Expenditures:
$135,100,000

Click to view the Final Audit Report

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31