Caltrans Logo

Passenger Information Systems

Description: ITS project including AVL, real-time passenger information system, computer aided dispatch, web and smart phone interface, head-sign, automatic voice announcement, and other components.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Montebello
Zip Code 90640
 
Senate District
30
Assembly District 58
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  20    5  
Increased Ridership  5      
Reduced Operating/Maintenance Cost  15      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
GLORIA GALLARDO (323) 887-4609   GGALLARDO@CITYOFMONTEBELLO.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $1 $1
PTMISEA-99314
$242 $0 $242
Non-bond Funding
State/Federal*
$1,611 $0 $1,611
Local**
$161 $0 $161
 
Total**** $2,014 $1 $2,015

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$2,014 $1 $2,015 $2,015 $2,015 $-0
 
Total* $2,014 $1 $2,015 $2,015 $2,015 $-0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/20/2010 

10/06/2011 
 

 
12/20/2010 

10/06/2011 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/22/2012 

03/31/2014 
 

 
08/22/2012 

03/31/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2014 

06/30/2014 
11/09/2016 

11/09/2017 
07/01/2016 

10/31/2017 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 20 5
Increased Ridership 5
Reduced Operating/Maintenance Cost 15

Bond Funding Cost
Adopted:
$241,680
Current Approved:
$241,680
Actual Expenditures:
$241,680

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31