Battery Electric Van Replacement Purchase

Description: Replacement of one or more gasoline 29' cutaway bus with battery electric transit passenger van with 8/1 ADA seating

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
23
Assembly District 34
Congressional District 23
 
Caltrans District
06
 
Project Benefits
 Benefit Baseline Actual
Reduced Emissions  25    20  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
CHRISTOPHER SMITH (760) 499-5041   CSMITH@RIDGECREST-CA.GOV
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$12 $2 $14
PTMISEA-99313
$114 $0 $114
PTMISEA-99314
$0 $0 $0
Non-bond Funding
State/Federal*
$324 $-228 $96
 
Total**** $451 $-226 $224

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$451 $-226 $224 $224 $224 $0
 
Total* $451 $-226 $224 $224 $224 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
06/01/2021 

06/30/2022 
 

 
04/15/2022 

09/01/2022 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2022 

07/31/2022 
03/14/2022 

03/01/2023 
06/01/2023 

06/30/2023 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Reduced Emissions 25 20

Bond Funding Cost
Adopted:
$126,274
Current Approved:
$114,377
Actual Expenditures:
$114,377

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31