Contra Costa College Transit Center Improvements

Description: Improvements to the transit center to make necessary repairs, enhance pedestrian safety, and improve ammenities at the station.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda
City Oakland
Zip Code 94612
 
Senate District
07, 09, 10
Assembly District 11, 14, 16, 18, 20
Congressional District 07, 09, 13
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  10      
Increased Ridership  10      
Reduced Operating/Maintenance Cost  80    13  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
KATE MILLER (510) 891-4859   KMILLER@ACTRANSIT.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$160 $0 $160
Non-bond Funding
Local**
$0 $165 $165
 
Total**** $160 $165 $325

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$160 $165 $325 $325 $325 $0
 
Total* $160 $165 $325 $325 $325 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2012 

09/30/2012 
08/21/2014 

08/21/2014 
12/31/2014 

01/31/2015 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2012 

04/30/2013 
03/02/2020 

03/02/2020 
04/01/2019 

09/30/2019 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/01/2013 

06/30/2014 
10/12/2020 

03/02/2020 
03/03/2020 

06/30/2020 
100   

 


Begin Closeout Phase

End Closeout Phase
07/01/2014 

12/31/2014 
10/12/2020 

10/12/2020 
06/15/2020 

08/06/2020 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 10
Increased Ridership 10
Reduced Operating/Maintenance Cost 80 13

Bond Funding Cost
Adopted:
$160,000
Current Approved:
$160,000
Actual Expenditures:
$160,000

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31