Caltrans Logo

Vehicle Replacement & Transit Improvements

Description: Vehicle Replacement & Transit Improvements

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma
City Santa Rosa
Zip Code 95404
 
Senate District
02
Assembly District 07
Congressional District 06
 
Caltrans District
04
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  2    20  
Reduced Emissions  4    10  
Reduced Operating/Maintenance Cost  1      
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
RACHE EDE (707) 543-3337   REDE@SRCITY.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-Interest
$0 $7 $7
PTMISEA-99313
$1,268 $-375 $893
Non-bond Funding
State/Federal*
$1,798 $-1,798 $0
 
Total**** $3,066 $-2,166 $900

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $0 $0 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$3,066 $-2,166 $900 $900 $900 $0
 
Total* $3,066 $-2,166 $900 $900 $900 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
09/01/2012 

11/01/2012 
08/19/2013 

08/19/2013 
10/01/2013 

12/01/2013 
100   

 


Begin Closeout Phase

End Closeout Phase
04/01/2014 

06/01/2014 
 

09/09/2014 
04/01/2014 

06/30/2014 
 

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 2 20
Reduced Emissions 4 10
Reduced Operating/Maintenance Cost 1

Bond Funding Cost
Adopted:
$1,268,194
Current Approved:
$893,348
Actual Expenditures:
$893,348

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31