Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Shelters, Amenities & Solar Lighting |
Description: Purchase and installation of new shelters, pads, benches, signage, solar lights, and other bus stop amenities.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Bernardino |
City | Hesperia |
Zip Code | 92345 |
Senate District |
17 |
Assembly District | 59 |
Congressional District | |
Caltrans District |
08 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 2 | 2 |
Increased Ridership | 4 | 4 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
KEVIN KANE | (760) 948-4330 | KKANE@VVTA.ORG |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$0 | $1 | $1 | ||||
PTMISEA-99313 |
$125 | $0 | $125 | ||||
Non-bond Funding | |||||||
State/Federal* |
$25 | $25 | $50 | ||||
Total**** | $150 | $26 | $176 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$25 | $25 | $50 | $0 | $0 | $50 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$125 | $1 | $126 | $126 | $126 | $0 | |
Total* | $150 | $26 | $176 | $126 | $126 | $50 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
06/01/2013 09/30/2013 |
03/23/2015 |
06/01/2013 07/03/2014 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/31/2014 03/15/2014 |
03/23/2015 03/23/2015 |
09/18/2014 10/30/2014 |
0 | |
0 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Increase System Reliability | 2 | 2 |
Increased Ridership | 4 | 4 |
Bond Funding Cost | |
---|---|
Adopted: |
$125,000 |
Current Approved: |
$125,000 |
Actual Expenditures: |
$125,000 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31