Park & Ride Facility Construction

Description: Construct a park and ride facility as part of the Western Placerville Interchanges on US 50. This location will contain approx. 192 parking stalls.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
El Dorado
City Diamond Springs, Ca
Zip Code 95619
 
Senate District
01
Assembly District 04, 10
Congressional District 04
 
Caltrans District
03
 
Project Benefits
 Benefit Baseline Actual
Increased Ridership  3    3  
Reduced Operating/Maintenance Cost  3    3  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
MINDY JACKSON (530) 642-5383   MJACKSON@ELDORADOTRANSIT.COM
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Bond Funding
PTMISEA-Interest
$0 $40 $40
PTMISEA-99313
$1,071 $160 $1,231
PTMISEA-99314
$200 $0 $200
Non-bond Funding
 
Total**** $1,271 $200 $1,470

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(06/30/2024
b=c-a
Current Approved
(06/30/2024
c
Cost to Date**
(06/30/2024
d
Cost Forecast
(06/30/2024
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$90 $-54 $36 $36 $36 $0
Right of Way
$0 $1 $1 $1 $1 $0
Construction
$1,181 $253 $1,433 $1,433 $1,433 $0
 
Total* $1,271 $200 $1,470 $1,470 $1,470 $0

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(06/30/2024)
c
% Complete
(06/30/2024)
d
Schedule Forecast
(06/30/2024)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/2013 

12/01/2013 
 

 
06/01/2013 

12/01/2013 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
02/01/2014 

06/30/2014 
 

 
02/01/2014 

12/31/2016 
 

 


Begin Right of Way Phase

End Right of Way Phase
06/30/2014 

10/31/2014 
 

 
06/30/2014 

10/31/2014 
 

 


Begin Construction Phase

End Construction Phase
01/01/2015 

10/31/2015 
04/12/2018 

02/13/2020 
02/01/2018 

11/04/2019 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2016 

06/30/2016 
04/12/2018 

08/25/2020 
01/01/2020 

12/31/2020 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increased Ridership 3 3
Reduced Operating/Maintenance Cost 3 3

Bond Funding Cost
Adopted:
$1,270,620
Current Approved:
$1,430,620
Actual Expenditures:
$1,430,620

 

Status as of June 30, 2024.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31