Sealed Corridor in Ventura County

Description: Construction of grade crossing improvements in Ventura County.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Ventura
City Ventura
Zip Code 93003
 
Senate District
27
Assembly District 38
Congressional District
 
Caltrans District
07
 
Project Benefits
 Benefit Baseline Actual
Increase System Reliability  5    5  
Reduced Operating/Maintenance Cost  10    10  
 
Project Contacts Agency Contact Person Telephone E-mail
PTMISEA
STEPHANIE YOUNG (805) 642-1591 X108   SYOUNG@GOVENTURA.ORG
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
PTMISEA-99313
$150 $-139 $11
Non-bond Funding
State/Federal*
$8,520 $4,800 $13,320
Local**
$0 $0 $0
 
Total**** $8,670 $4,660 $13,330

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $0 $0 $11 $11 $-11
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$8,670 $4,660 $13,330 $13,520 $13,520 $-189
 
Total* $8,670 $4,660 $13,330 $13,530 $13,530 $-200

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

01/01/2013 
 

 
 

01/01/2013 
100   

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/2012 

06/01/2013 
 

 
10/01/2012 

06/01/2013 
100   

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
12/31/2013 

12/31/2014 
 

04/07/2017 
12/31/2013 

02/01/2017 
100   

 


Begin Closeout Phase

End Closeout Phase
01/01/2015 

03/31/2015 
04/07/2017 

05/02/2018 
03/01/2017 

03/01/2018 
100   

 


????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Increase System Reliability 5 5
Reduced Operating/Maintenance Cost 10 10

Bond Funding Cost
Adopted:
$150,000
Current Approved:
$10,621
Actual Expenditures:
$10,621

Click to view the Final Audit Report

 

Status as of December 31, 2023.

PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31